Contract No: HK/2015/01 Wanchai
Development Phase II and Central Wanchai Bypass Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/E, Further
Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B and FEP-11/364/2009/E, FEP-12/364/2009/D Monthly Environmental Monitoring &
Audit Report
- APRIL 2017 -
|
CLIENTS: |
|
Civil Engineering
and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond Dai Environmental Team
Leader |
|
DATE: |
|
May 2017 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
3
status of regulatory compliance..
3.1 Status of Environmental Licensing and
Permitting under the Project
5.2 Real Time Noise Monitoring Results
5.3 Air Quality Monitoring Results
6.3 Review of the Reasons for and the
Implications of Non-compliance.
6.4 Summary of action taken in the event of
and follow-up on non-compliance.
7 Cumulative Construction
Impact due to the Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table
2.1 Schedule 2 Designated Projects under
this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 3.1 Summary
of the current status on licences and/or permits on environmental
protection pertinent to the Project
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.3 Summary
of submission status under FEP-02/364/2009
Table 3.4 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.5 Summary
of submission status under FEP-01/364/2009
Table 3.6 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.7 Summary
of submission status under FEP-05/364/2009/A
Table 3.8 Cumulative
Summary of Valid Licences and Permits under Contract no.
Table 3.9 Summary
of submission status under FEP-06/364/2009/A
Table 3.10 Cumulative Summary of Valid
License and Permits under Contract no. HY/2009/19
Table 3.11
Summary of submission status under FEP-07/364/2009/D
Table 3.12 Cumulative Summary of Valid
License and Permits under Contract no. HK/2012/08
Table 3.13 Summary of submission status under FEP-12/364/2009/D
Table 3.14 Cumulative Summary of Valid
License and Permits under Contract no. HY/2010/08
Table 3.15 Summary of submission status under
FEP-10/364/2009/B
Table 3.16 Cumulative Summary of Valid
License and Permits under Contract no. HY/2011/08
Table 3.17 Summary of submission status under FEP-11/364/2009/E
Table 4.1 Noise Monitoring
Stations
Table 4.2 Real
Time Noise Monitoring Stations
Table 4.3 Air
Quality Monitoring Stations
Table 5.1 Noise
Monitoring Stations for Contract no. HY/2009/18
Table 5.2 Noise
Monitoring Station for Contract no HK/2009/01 and HK/2009/02
Table 5.3 Noise
Monitoring Stations for Contract no. HY/2009/15
Table 5.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 5.5 Noise Monitoring
Stations for Contract no. HY/2010/08
Table 5.6 Noise
Monitoring Stations for Contract no. HY/2011/08
Table 5.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 5.8 Real
Time Noise Monitoring Stations for Contract no. HY/2011/08
Table 5.9 Air
Quality Monitoring Station for Contract no. HY/2009/18
Table 5.10 Air Quality Monitoring
Station for Contract no. HK/2009/01
Table 5.11 Air Quality Monitoring
Station for Contract no. HK/2009/02
Table 5.12 Air Quality Monitoring
Stations for Contract no. HY/2009/15
Table 5.13 Air Quality
Monitoring Station for Contract no. HY/2009/19
Table 5.14 Air Quality
Monitoring Station for Contract no. HK/2012/08
Table 5.15 Air Quality Monitoring Stations for Contract no. HY/2010/08
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Table 5.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 5.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 5.21 Details of Waste Disposal
for Contract no. HY/2009/19
Table 5.22 Details of Waste Disposal
for Contract no. HK/2012/08
Table 5.23 Details of Waste Disposal
for Contract no. HY/2010/08
Table 5.24 Details of Waste Disposal for Contract
no. HY/2011/08
Table 8.1 Summary of
Environmental Inspections for Contract no. HY/2009/15
Table 8.2 Summary of Environmental
Inspections for Contract no. HY/2009/18 (NOT USED)
Table 8.3 Summary of
Environmental Inspections for Contract no. HY/2009/19 (NOT USED)
Table 8.4 Summary of
Environmental Inspections for Contract no. HK/2009/01 (NOT USED)
Table 8.5 Summary of Environmental Inspections for
Contract no. HK/2009/02
Table 8.6 Summary of
Environmental Inspections for Contract no. HK/2012/08
Table
8.7 Summary of Environmental
Inspections for Contract no. HY/2010/08
Table 8.8 Summary of
Environmental Inspections for Contract no. HY/2011/08)
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be
commenced in Coming Reporting Month
LIST OF FIGUREs
Figure 2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring
Results and Graphical Presentations
Appendix
5.4 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix 9.1 Complaint Log
Appendix 10.1 Construction Programme of Individual Contracts
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) - Central
Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
·
Rectification works for the defects recorded in the inspection for the
end of maintenance period of Observation Deck and Staircase ST-01
·
Rectification works for cross road ducts
·
rectification works for cracks/joints with water leakage inside OHVD
cells
·
Backfilling works
·
Construction of temporary wall for inside tunnel
·
Blinding layer for Hung Hing Road Flyover
·
Cleaning of cross road duct & carrier drain
·
Rectification works against water leakage and remedial works against
concrete defects of the tunnel structure
·
Outstanding works inside tunnel
·
Concreting for base slab
·
Removal of ELS layer S2 & S3
·
Tunnel wall structure
·
Concreting for roadside barrier
·
Erection of scaffolding for construction of OHVD
·
Concreting for OHVD slab
·
Erection of scaffolding for construction of top slab
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge Demolition / Construction
·
Hotel Carpark Reinstatement
·
Bridge E noise barrier installation
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
·
Removal of temporary works including beams, columns and footings for TB
bridge
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction of MVB and CWB Tunnel and Slip Road 1
·
Construction of drainage
·
Back-filling at CWB tunnel
Contract
no. HY/2010/08 –Central - Wan Chai Bypass (CWB) –Tunnel (Slip Road 8) under
FEP-10/364/2009/B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
Noise Monitoring
Air Quality Monitoring
The 24hr TSP monitoring at CMA3a was
rescheduled from 06 March 2017 to 07 March 2017;
The 24hr TSP monitoring at CMA4a was
rescheduled from 06 March 2017 to 07 March 2017;
Complaints, Notifications of Summons
and Successful Prosecutions
Site Inspections and Audit
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works under
FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification works for the defects for the end of maintenance period of
Observation Deck and Staircase ST-01.
·
Rectification works for cross road ducts
·
Rectification works for
cracks/joints with water leakage inside OHVD cells
·
Tunnel backfilling (rock fill Type A, Type B and filter material)
·
Construction of temporary wall.
·
Concreting blinding layer for Hung Hing Road flyover.
·
Rebar fixing and concreting of HHR flyover.
·
Remedial works of tunnel wall, base slab and OHVD.
·
General cleaning and rectification works of OHVD, tunnel base slab,
carrier drain, cross road duct and manhole gully.
·
Rebar fixing and concreting of base slab and walls.
·
Rebar fixing and concreting of roadside barrier.
·
Rebar fixing and concreting of OHVD slab.
·
Rebar fixing and concreting of top slab.
·
Erect scaffolding for OHVD and top slab.
·
Tree Pruning Works at Fleming Road (VO No. 237)
·
Tree pruning works at Fleming Road
·
Sewage Works at Hung Hing Road and Wan Shing Street
·
Trial pit at Hung Hing Road for sewage works.
·
Construction of manhole for Wan Shing Street sewage works
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
·
Re-surfacing work at Hung Hing Road
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Hing Fat Street modification works
·
Bridge Demolition / Construction
·
Hotel Carpark Reinstatement
·
Oil Street drainage works
·
Bridge E noise barrier installation
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
·
Removal of temporary works including beams, columns and footings for TB
bridge
·
Installation of skin parapet on TB bridge
·
Construction of metal roof for FEHD
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
·
Grouting
·
Construction of Slip Road 1
·
Construction of drainage
·
Back-filling at CWB tunnel
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to work as the
Environmental Team (ET) under Environmental Permit no. EP-364/2009/E and
Further Environmental permit nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This report presents the environmental monitoring and auditing work
carried out in accordance to the Section
10.3 of EM&A Manual and “Environmental Monitoring and Audit
Requirements” under Particular Specification Section 27.
1.1.3.
This report documents the finding of EM&A
works for Environmental Permit (EP) no. EP-364/2009/E, Further Environmental
Permit (FEP) nos. FEP-01/364/2009, FEP-02-364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A FEP-07/364/2009/D, FEP-09/364/2009/B,
FEP-10/364/2009/B, FEP-11/364/2009/E and FEP-12/364/2009/D during the period 27 March 2017 to 26 April 2017.
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results – summarizes the monitoring results obtained
in the reporting period.
Section
6 Compliance
Audit – summarizes the auditing of monitoring
results, all
exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Environmental Site Audit –
summarizes the findings of weekly site inspections undertaken within the reporting
period, with a review of any
relevant follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1.
“Wan Chai Development phase II and Central-Wan Chai Bypass” and
“Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called
“the Project”) are Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The
Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development
phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been
approved on 31 August 2001 and 11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development Phase II (WDII) is to provide
land at Wan Chai North and North Point for construction of the Central-Wan Chai
Bypass and Island Eastern Corridor Link (CWB). Land formed under the project
will be developed as a world-class waterfront promenade joining that at the new
Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB to provide relief to
the very congested east-west Connaught Road Central/Harcourt Road / Gloucester
Road Corridor (the Corridor) which is currently operating beyond its capacity.
The CWB will provide relief to the existing congestion along the Corridor and
cater for the anticipated growth of traffic on Hong Kong Island. Without the
CWB and its access roads, there will not be sufficient capacity to serve the
heavy traffic demands at both strategic and local levels.
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km in length, and tunnel
approximately 3.7 km in length defined from the connection with the existing
Rumsey Street Flyover in Central, through to a connection with the existing
Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street Flyover to provide road
connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road system in the Wan Chai
North and Causeway Bay area;
·
Associated road lighting, road signing, traffic control and surveillance
system; and
·
Other associated works.
2.2.3.
The project also contains various Schedule 2 DPs that, under the EIAO,
require Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason
for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road
tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in
length |
DP2 |
Road P2 and other roads which are classified as
primary/district distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging
works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging
operation less than 100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter
more than 1,200 mm and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from
Wan Chai to Tsim Sha Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a
seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project, there are a number of
contracts sub-dividing the whole works area into different work areas to be
commenced. Contractors of
individual contracts will be required by the EP holder to apply Further
Environmental Permits such that the impact monitoring stations are sub-divided accordingly to
facilitate the implementation of EM&A programme and to streamline the
EM&A reporting for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield
Depot – Advanced piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central
Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works |
DP1,
DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East(CWB Tunnel) |
DP1 |
26
April 2011 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) |
DP1,DP3 |
13
July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link |
DP1 |
24
March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai
Bypass over MTR Tsuen Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.4.1.
Civil Engineering and Development Department
and Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and lines of communication with
respect to environmental protection works are shown in Figure 2.2.
Key personnel and contact particulars are summarized in Table 2.3:
Table 2.3 Contact Details of Key
Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912
3328 |
|
Chun Wo – Leader
Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2587
1878 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Environmental
Officer |
Mr.
Terry Tsang |
6683
9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827
9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint
Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570
8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Site Agent |
Mr. David Lau |
3758 8879 |
|||
Deputy Site Agent |
Mr. Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. James Chan |
3757 8217 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
3973
0803 |
|
Environmental Officer |
Mr. Chris Chan |
3973
0885 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2865 5229 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
2566 2192 |
||
Contractor’s
Representative |
Mr. Rex Lau |
3557
6405 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6347 |
|||
China State- Build King JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|||
China State |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Chris
Leung |
9210
7116 |
2566
8061 |
Site
Agent |
Mr. Francis
Suen |
3557
6407 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6466 |
|||
Environmental
Supervisor |
Mr. Desmond
Ho |
3557
6465 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Site Agent |
Mr. Colman Wong |
2823 1410 |
21406799 |
Environmental
Officer |
Mr.
Malcolm Leung |
3973 0850 |
|||
Environmental
Supervisor |
Ms. Christy So |
3973 1065 |
|||
Ramboll Environ Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics
Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond
Dai |
2882
3939 |
2882 3331 |
2.4.3.
In this reporting month, the principal work
activities of individual contracts are included as follows:
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange under FEP-05/364/2009/A
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
·
Rectification works for the defects recorded in the inspection for the
end of maintenance period of Observation Deck and Staircase ST-01
·
Rectification works for cross road ducts
·
rectification works for cracks/joints with water leakage inside OHVD
cells
·
Backfilling works
·
Construction of temporary wall for inside tunnel
·
Blinding layer for Hung Hing Road Flyover
·
Cleaning of cross road duct & carrier drain
·
Rectification works against water leakage and remedial works against
concrete defects of the tunnel structure
·
Outstanding works inside tunnel
·
Concreting for base slab
·
Removal of ELS layer S2 & S3
·
Tunnel wall structure
·
Concreting for roadside barrier
·
Erection of scaffolding for construction of OHVD
·
Concreting for OHVD slab
·
Erection of scaffolding for construction of top slab
Contract no. HY/2009/15 -
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Bridge Demolition / Construction
·
Hotel Carpark Reinstatement
·
Bridge E noise barrier installation
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
·
Removal of temporary works including beams, columns and footings for TB
bridge
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
·
Grouting
·
Construction of MVB and CWB Tunnel and Slip Road 1
·
Construction of drainage
·
Back-filling at CWB tunnel
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009/B
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
2.4.4.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
·
Drainage works
·
Road works
·
Landscaping works
·
Maintenance works
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
·
Reinstatement of amenity area
·
Road and Drain works
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
·
Rectification works for the defects for the end of maintenance period of
Observation Deck and Staircase ST-01.
·
Rectification works for cross road ducts
·
Rectification works for
cracks/joints with water leakage inside OHVD cells
·
Tunnel backfilling (rock fill Type A, Type B and filter material)
·
Construction of temporary wall.
·
Concreting blinding layer for Hung Hing Road flyover.
·
Rebar fixing and concreting of HHR flyover.
·
Remedial works of tunnel wall, base slab and OHVD.
·
General cleaning and rectification works of OHVD, tunnel base slab,
carrier drain, cross road duct and manhole gully.
·
Rebar fixing and concreting of base slab and walls.
·
Rebar fixing and concreting of roadside barrier.
·
Rebar fixing and concreting of OHVD slab.
·
Rebar fixing and concreting of top slab.
·
Erect scaffolding for OHVD and top slab.
·
Tree Pruning Works at Fleming Road (VO No. 237)
·
Tree pruning works at Fleming Road
·
Sewage Works at Hung Hing Road and Wan Shing Street
·
Trial pit at Hung Hing Road for sewage works.
·
Construction of manhole for Wan Shing Street sewage works
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and
TPCWAW
·
Reinstatement work at the PRE Office car park area
·
Re-surfacing work at Hung Hing Road
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
·
Approach ramp sheet piling, pre-bored piling and top soil removal works
·
Hing Fat Street modification works
·
Bridge Demolition / Construction
·
Hotel Carpark Reinstatement
·
Oil Street drainage works
·
Bridge E noise barrier installation
·
IEC noise enclosure/barrier installation
·
Excavation / Construction of retaining wall
·
Removal of temporary works including beams, columns and footings for TB
bridge
·
Installation of skin parapet on TB bridge
·
Construction of metal roof for FEHD
Contract no. HK/2012/08 – Wan Chai
Development Phase II – Central- Wan Chai Bypass at Wan Chai West under
FEP-12/364/2009/D
·
Grouting
·
Construction of Slip Road 1
·
Construction of drainage
·
Back-filling at CWB tunnel
Contract no. HY/2010/08 –Central - Wan
Chai Bypass (CWB) –Tunnel (Slip Road 8) under FEP-10/364/2009
·
Tree protection works next to existing BGO,
·
Drainage improvement works,
·
Utility diversion works,
·
Retaining wall works
·
ELS works,
·
Construction works for subway extension
Contract no. HY/2011/08 – Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/E
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
·
Construction of Tunnel Thermal Barrier
·
Installation of Electricals and Mechanicals
·
Installation of Tunnel Features
3.1.1.
A summary of the current status on licences and/or permits on
environmental protection pertinent to the Project is shown in Table 3.1.
Table 3.1 Summary of the current status
on licences and/or permits on environmental protection pertinent to the Project
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Superseded |
Environmental Permit |
EP-364/2009/D |
24 Nov 2015 |
Superseded |
Environmental Permit |
EP-364/2009/E |
22 Dec 2016 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Surrendered |
Further
Environmental Permit |
FEP-06/356/2009 |
5 March 2013 |
Valid |
Further
Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
24 Mar 2010 |
Valid |
|
Further Environmental Permit |
21 Apr 2010 |
Valid |
|
Further Environmental Permit |
12 July 2010 |
Surrendered |
|
Further Environmental Permit |
14 Oct 2010 |
Surrendered |
|
Further Environmental Permit |
15 Nov 2010 |
Valid |
|
Further Environmental Permit |
22 Nov 2010 |
Valid |
|
Further Environmental Permit |
25 Feb 2011 |
Superseded |
|
Further Environmental Permit |
24 Nov 2015 |
Valid |
|
Further Environmental Permit |
15 June 2012 |
Surrendered |
|
Further Environmental Permit |
FEP-09/364/2009/B |
5 March 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
Superseded |
Further Environmental Permit |
FEP-11/364/2009/E |
22 Dec 2016 |
Valid |
Further Environmental Permit |
FEP-12/364/2009/D |
01 Aug 2016 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project, the status of permits
and/or licences under the individual contract(s) are presented as below:
Contract no. HY/2009/17 – Central – Wan Chai
Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works under
FEP-03/364/2009
3.1.3.
The construction works was completed and the
FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.
Contract no. 04/HY/2006 – Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
3.1.4. The construction works was completed, and the FEP-04/HY/2006 was
surrendered by the Contractor on 11 February 2011.
Contract no. HK/2010/06 - Wan Chai
Development Phase II - Central - Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
3.1.5. The construction works was completed, and the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
Contract no.
HK/2009/01 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre – Tunnel Works under FEP-02/364/2009
3.1.6.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-02/364/2009 for contract no. HK/2009/01 are shown in Table 3.2 and Table 3.3.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS1004-16 |
28 Sep 2016 |
29 Sep 2016 to 27 Mar 2017 |
Expired |
GW-RS1079-16 |
27 Oct 2016 |
27 Oct 2016 to 20 Apr 2017 |
Expired |
|
GW-RS1241-16 |
12 Dec 2016 |
15 Dec 2016 to 06 Jun 2017 |
Valid |
|
GW-RS1240-16 |
12 Dec 2016 |
13 Dec 2016 to 06 Jun 2017 |
Valid |
|
GW-RS1233-16 |
12 Dec 2016 |
14 Dec 2016 to 06 Jun 2017 |
Valid |
|
GW-RS1234-16 |
12 Dec 2016 |
20 Dec 2016 to 19 Jun 2017 |
Valid |
|
Discharge License |
WT00024952-2016 |
06 Jul 2016 |
31 Jul 2021 |
Valid |
WT00021138-2015 |
17 Mar 2014 |
31 Mar 2020 |
Valid |
|
Billing account under
Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Table
3.3 Summary of submission status under FEP-02/364/2009
EP Condition |
Submission |
Date of
Submission |
Condition 2.7 & 2.8 |
Works Schedule and Location Plan |
18 May
2011 |
Condition 2.6 |
Environmental Management Organization Chart |
18 May
2011 |
Condition 1.12 |
Commencement Date of Works |
20 Jun
2011 |
Condition 2.9 |
Noise Management Plan |
10 Jun 2011 |
Condition 2.11 |
Landscape Plan (Rev.4) |
8 July 2015 |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
3.1.7.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-01/364/2009 for contract no. HK/2009/02 are shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid
Licences and Permits under Contract no. HK/2009/02
Permits and/or Licenses |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
N/A |
Valid |
FEP-01/364/2009 |
24 Mar
2010 |
N/A |
Valid |
|
Notification
of Works Under APCO |
313962 |
2 Feb
2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-pilling
equipment |
GW-RS1153-16 |
17 Nov 2016 |
18 Nov 2016 to 13 May 2017 |
Cancelled |
GW-RS1047-16 |
13 Oct 2016 |
26 Oct 2016 to 25 Apr 2017 |
Expired |
|
GW-RS1140-16 |
11 Nov 2016 |
14 Nov 2016 to 09 May 2017 |
Valid |
|
GW-RS1297-16 |
15 Dec 2016 |
16 Dec 2016 to 14 Jun 2017 |
Valid |
|
GW-RS1305-16 |
22 Dec 2016 |
24 Dec 2016 to 13 Jun 2017 |
Valid |
|
GW-RS0289-17 |
31 Mar 2017 |
02 Apr 2017 to 02 Jul /2017 |
Valid |
|
GW-RS0314-17 |
07 Apr 2017 |
11 Apr 2017 to 04 Oct 2017 |
Valid |
|
GW-RS0338-17 |
13 Apr 2017 |
28 May 2017 to 27 Aug 2017 |
Valid |
|
GW-RS0334-17 |
18 Apr 2017 |
21 Apr 2017 to 06 Oct 2017 |
Valid |
|
GW-RS0348-17 |
18 Apr 2017 |
25 Apr 2017 to 24 Oct 2017 |
Valid |
|
Water
Discharge License |
WT00022295-2015 |
12 Aug 2015 |
31 July 2020 |
Valid |
WT00025276-2016 |
19 Sep 2016 |
31 July 2021 |
Valid |
|
Billing
Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration
as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Table
3.5 Summary of submission status
under FEP-01/364/2009
EP Condition |
Submission |
Date
of
Submission |
Condition 2.7
and 2.8 |
Works
Schedule and Location Plan |
14 Jun 2011 |
Condition 2.6 |
Environmental
Management Organization Chart |
14 Jun 2011 |
Condition 1.12 |
Commencement
Date of Works |
21 Jun 2011 |
Condition
2.11 |
Landscape Plan (Revision B) |
20 Nov
2012 |
Condition 2.9 |
Noise Management Plan (Revision B) |
13 Jan
2012 |
Contract no. HY/2009/18 – Central – Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
3.1.8.
Summary of the current status on licences and/or permits on
environmental protection pertinent and submission under FEP-05/364/2009A for contract no. HY/2009/18 are shown in Table 3.6 and Table
3.7.
Table
3.6 Cumulative Summary of Valid
Licences and Permits under Contract no. HY/2009/18
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
FEP-05/364/2009/A |
15
Nov 2010 |
Permit
issued |
Valid |
Notification
of Works Under APCO |
322293 |
07
Oct 2010 |
Notified |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS1164-16 |
17 Nov 2016 |
1 Dec 2016 to 31 Mar 2017 |
Cancelled |
GW-RS1161-16 |
17 Nov 2016 |
1 Dec 2016 to 31 Mar 2017 |
Expired |
|
GW-RS1307-16 |
21 Dec 2016 |
23 Dec 2016 to 30 Apr 2017 |
Valid |
|
GW-RS1338-16 |
28 Dec 2016 |
01 Jan 2017 to |
Valid |
|
Discharge
Licenses |
WT00013967-2012 |
17
Sep 2012 |
30
Sep 2017 |
Cancelled |
WT00014966-2013 |
08 Jan 2013 |
31 Jan 2018 |
Cancelled |
|
WT00020725-2015 |
14
Jan 2015 |
30
Jul 2017 |
Valid |
|
WT00024255-2016 |
18
May 2016 |
31
Jan 2021 |
Valid |
|
Registration
as a Chemical Waste Producer |
WPN: 8335-121-L1048-04 |
17
Dec 2010 |
N/A |
Registration completed |
Billing Account under Waste Disposal Ordinance
(Land) |
Account No.: 7011587 |
11
Oct 2010 |
Account approved |
Valid |
Table 3.7 Summary of submission status
under FEP-05/364/2009/A
EP Condition |
Submission |
Date
of
Submission |
Condition 2.9 |
Noise Management Plan |
01 March 2011 |
Condition 2.10 |
Landscape Plan (Rev. 6) |
19 May 2014 |
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
3.1.9.
Summary of the current status on licences
and/or permits on environmental protection pertinent and submission
under FEP-06/364/2009/A for contract no. HY/2009/15 are shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary
of Valid Licences and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS1174-16 |
18 Nov 2016 |
24 Nov 2016 to 23 May 2017 |
Valid |
Registration as a Chemical Waste
Producer |
WPN: 5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7011553 |
30 Sep 2010 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance (Disposal by Vessel) |
7011761 |
30 Dec 2016 |
17 Jan 2016 to 16 Apr 2017 |
Expired |
Water Discharge Licence (Discharge
at TPCWAW) |
WT00020601-2014 |
18 Mar 2015 |
18 Mar 2015 to 31 Mar 2017 |
Expired |
Water Discharge License (Discharge
at TS1) |
WT00024874-2016 |
20 Jul 2016 |
20 Jul 2016 to 31 Mar 2021 |
Valid |
WT00024951-2016 |
8 Jul 2016 |
8 Jul 2016 to 31 Dec 2017 |
Valid |
Table 3.9 Summary of submission status under
FEP-06/364/2009/A
EP
Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main
Construction Companies |
11 Mar
2011 |
Amendment for Management
Organization of Main Construction Companies |
16 May
2011 |
|
Condition 2.7 |
Works Schedule |
15 Mar
2011 |
Condition 2.8 |
Location Plan |
15 Mar
2011 |
Condition 2.9 |
Noise Management Plan |
6 May
2011 |
Condition
2.10 |
Landscape
Plan (Rev.3) |
30 Jan 2015 |
Contract no. HY/2009/19 – Central – Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
3.1.10.
The current status on licences and/or permits
on environmental protection pertinent and submission
under FEP-07/364/2009/D for contract no. HY/2009/19 are shown in Table 3.10 and Table
3.11.
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid
Period/ Expiry Date |
Status |
Further
Environmental Permit |
25 Feb 2011 |
N/A |
Valid |
|
24 Nov 2015 |
N/A |
Valid |
||
Notification
of Works Under APCO |
326160 |
24 Jan 2011 |
N/A |
Valid |
Registration
as a Waste Producer |
7012306 |
10
Feb 2011 |
N/A |
Valid |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24
Mar 2011 |
N/A |
Valid |
Application
for Vessel Disposal |
7012306 |
21
July 2011 |
N/A |
Valid |
Construction
Noise Permits (CNP) for non-piling equipment |
GW-RS1251-16 |
07 Dec 2016 |
18 Dec 2016 to 17 Jun 2017 |
Valid |
GW-RS1372-16 |
06 Jan 2017 |
11 Jan 2017 to 07 Apr 2017 |
Expired |
|
GW-RS0238-17 |
23-Mar-17 |
08 Apr 2017 to 07 Jun
2017 |
Valid |
|
Water
Discharge License |
WT00025282-2016 |
15 Sep
2016 |
30-Sept-21 |
Valid |
Dumping Permit (Approach Ramp) (Type
1 – Open Sea Disposal) |
EP/MD/17-078 |
01
Oct 2016 |
31
Mar 2017 |
Valid |
Table 3.11 Summary of submission status under
FEP-07/364/2009/D
EP Condition |
Submission |
Date of Submission |
Condition 2.13 |
Landscape Plan (Rev.5) |
09 December 2016 |
Condition 2.9 |
Noise Management Plan (Rev.4) |
15
February 2016 |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West
3.1.11.
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-12/364/2009/D for contract no.
HK/2012/08 showed in Table 3.12 and Table 3.13.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid
Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-09/364/2009/B |
5 Mar 2013 |
N/A |
Valid |
FEP-12/364/2009/D |
1 Aug 2016 |
N/A |
Valid |
|
FEP-06/356/2009 |
5 March 2013 |
N/A |
Valid |
|
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste
Producer |
5213-134-C3790-01 |
30 Jun 2016 |
N/A |
Valid |
Billing Account under Waste
Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS1336-16 |
29 Dec 2016 |
13 Jan 2017 to 12 Jul 2017 |
Valid |
GW-RS1371-16 |
5 Jan 2017 |
9 Jan 2017 to 8 Jul 2017 |
Valid |
|
GW-RS0098-17 |
1 Feb 2017 |
26 Feb 2017 to 25 Aug 2017 |
Valid |
|
Water Discharge Licence |
WT00018223-2014 |
28 Jan 2014 |
31 Jan 2019 |
Cancelled |
WT00020594-2014 |
22 Dec 2014 |
31 Jan 2019 |
Valid |
Table
3.13 Summary
of submission status under FEP-12/364/2009/D
Submission |
Date of Submission |
|
Condition 2.9 |
Noise Management Plan (Rev.2) |
9 July 2013 |
Condition 2.14 |
Landscape Plan (Rev.4) |
24 August 2015 |
Contract
no. HY/2010/08 –Central – Wanchai Bypass Tunnel – Tunnel (Slip Road 8)
3.1.12.
The current status on licences and/or permits on environmental
protection pertinent and submission under FEP-10/364/2009/B for contract no.
HK/2012/08 showed in Table 3.14 and Table 3.15.
Table
3.14 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2010/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-10/364/2009/B |
26
Jul 2013 |
NA |
Valid |
FEP-07/356/2009 |
26
Jul 2013 |
NA |
Valid |
|
Notification of Works Under APCO |
357176 |
2013-04-02 |
NIL |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
2013-03-27 |
NIL |
Valid |
Billing Account under Waste Disposal
Ordinance |
7017170 |
2013-03-27 |
NIL |
Valid |
Water Discharge
License |
WT0001651-2013 |
2013-07-09 |
2018-07-28 |
Cancelled |
WT00020468-2014 |
2014-12-03 |
2018-07-31 |
Valid |
|
Construction Noise Permit (CNP) for
non-piling equipment |
GW-RS1232-16 |
08 Dec 2016 |
08 Dec 2016 to 01 June 2017 |
Cancelled |
GW-RS1194-16 |
30 Nov 2016 |
30 Nov 2016 to 24 May 2017 |
Cancelled |
|
GW-RS1129-16 |
24 Nov 2016 |
24 Nov 2016 to 22 May 2017 |
Cancelled |
|
GW-RS0977-16 |
21 Sep 2016 |
15 Nov 2016 to 14 May 2017 |
Cancelled |
|
GW-RS0029-17 |
19 Jan 2017 |
19 Jan 2017 to 02 Jul 2017 |
Cancelled |
|
GW-RS0969-16 |
23 Nov 2016 |
23 Nov 2016 to 22 May 2017 |
Cancelled |
|
GW-RS1182-16 |
29 Nov 2016 |
30 Nov 2016 to 24 May 2017 |
Cancelled |
|
GW-RS0134-17 |
22 Feb 2017 |
23 Feb 2017 to 19 Aug 2017 |
Cancelled |
|
GW-RS0562-16 |
28 Oct 2016 |
28 Oct 2016 to 26 Apr 2017 |
Cancelled |
|
GW-RS0971-16 |
19 Sep 2016 |
22 Oct 2016 to 20 Apr 2017 |
Expired |
|
GW-RS1254-16 |
10 Dec 2016 |
10 Dec 2016 to 07 Jun 2017 |
Valid |
|
GW-RS0086-17 |
31 Jan 2017 |
31 Jan 2017 to 30 Jul 2017 |
Valid |
|
GW-RS0092-17 |
31 Jan 2017 |
31 Jan 2017 to 31 Jul 2017 |
Valid |
|
GW-RS1366-16 |
06 Jan 2017 |
06 Jan 2017 to 26 Jun 2017 |
Valid |
|
GW-RS0201-17 |
18 Mar 2017 |
18 Mar 2017 to 17 Sep 2017 |
Valid |
|
GW-RS0347-17 |
27 Apr 2017 |
27 Apr 2017 to 18 Oct 2017 |
Valid |
|
GW-RS0360-17 |
20 Apr 2017 |
20 Apr 2017 to 19 Oct 2017 |
Valid |
|
GW-RS0290-17 |
08 Apr 2017 |
08 Apr 2017 to 30 Sep 2017 |
Valid |
Table
3.15 Summary
of submission status under FEP-10/364/2009/B
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.3) |
03 January 2014 |
Condition 2.14 |
Landscape Plan (Rev.2) |
19 May 2014 |
Condition 2.16 |
Additional Mitigation Plan (Rev.2) |
18 February 2015 |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
3.1.13.
The current status on licenses and/or permits on environmental
protection pertinent and submission under FEP-11/364/2009/E for contract no.
HY/2011/08 showed in Table 3.16 and Table 3.17.
Table
3.16 Cumulative Summary of Valid Licences and
Permits under Contract no. HY/2011/08
Permits
and/or Licences |
Reference
No. |
Issued
Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-11/364/2009/B |
2 May 2014 |
N/A |
Valid |
FEP-11/364/2009/E |
22 Dec 2014 |
N/A |
Valid |
|
Notification of Works Under APCO |
LCAC-EN-LE-00017 |
7 Mar 2014 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-121-L2837-01 |
19 Apr 2016 |
N/A |
Registered |
5213-151-L2837-02 |
24 May 2016 |
N/A |
Registered |
|
5213-134-L2898-01 |
16 Nov 2015 |
N/A |
Registered |
|
Billing Account under Waste Disposal Ordinance |
7019640 |
27 Mar 2014 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling
equipment |
GW-RS1089-16 |
28 Oct 2016 |
01 Nov 2016 to |
Valid |
GW-RS1151-16 |
17 Nov 2016 |
01 Dec 2016 to 31 May 2017 |
Valid |
|
GW-RS1168-16 |
17 Nov 2016 |
01 Dec 2016 to 31 May 2017 |
Valid |
|
GW-RS1169-16 |
18 Nov 2016 |
18 Nov 2016 to |
Valid |
|
GW-RS1178-16 |
17 Nov 2016 |
01 Dec 2016 to 31 May 2017 |
Valid |
|
GW-RS1134-16 |
28 Dec 2016 |
01 Jan 2017 to |
Valid |
|
GW-RS1137-16 |
28 Dec 2016 |
01 Jan 2017 to |
Valid |
|
GW-RS0068-17 |
24 Jan 2017 |
01 Feb 2017 to |
Valid |
|
GW-RS0100-17 |
1 Feb 2017 |
03 Feb 2017 to 31 Jul 2017 |
Valid |
|
GW-RS0139-17 |
23 Feb 2017 |
01 Mar 2017 to 31 Aug 2017 |
Valid |
|
GW-RS0146-17 |
23 Feb 2017 |
01 Mar 2017 to 31 Aug 2017 |
Valid |
|
GW-RS0260-17 |
27 Mar 2017 |
29 Mar 2017 - |
Valid |
|
GW-RS0294-17 |
31 Mar 2017 |
06 Apr 2017 - 30 Sep 2017 |
Valid |
|
GW-RS0359-17 |
25 Apr 2017 |
01 May 2017 - 31 Oct 2017 |
Valid |
|
Water Discharge Licence |
WT00020242-2014 |
04
Nov 2014 |
30
Nov 2019 |
Cancelled |
WT00022046-2015 |
15
Jul 2015 |
31
Jul 2019 |
Valid |
|
WT00022753-2015 |
3
May 2016 |
30
Apr 2021 |
Valid |
|
WT00024561-2016 |
30
May 2016 |
31
May 2021 |
Valid |
|
WT00022046-2015 |
15
Jul 2015 |
31
Jul 2019 |
Valid |
Table 3.17 Summary
of submission status under FEP-11/364/2009/E
EP Condition |
Submission |
Date of Submission |
Condition 2.9 |
Noise Management Plan (Rev.4) |
08 November 2016 |
Condition 2.14 |
Landscape Plan (Rev.2) |
18 Feb 2015 |
Condition 2.13 a) |
Operational Air Quality Management Plan for West Ventilation Building
(Rev.0) |
25 Nov 2014 |
Condition 2.13 b) |
Operational Air Quality Management Plan for Central Ventilation
Building (Rev.0) |
03 March 2017 |
Condition 2.13 c) |
Operational Air Quality Management Plan for East Ventilation Building
and East Vent Shaft (Rev.0) |
18 Feb 2015 |
Condition 2.13 d) |
Operational Air Quality Management Plan for an Electrostatic
Precipitator system for EVB Operation (Rev.0) |
06 April 2017 |
Condition 2.13 e) |
Operational Air Quality Management Plan for ventilation system of
Eastern Portal of the CWB Tunnel (Rev.0) |
23 October 2016 |
Noise
Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are listed and shown in Table
4.1 and Figure 4.1.
Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.1 Noise Monitoring Stations
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon-day
Gun Area |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist
Church Henrietta Secondary School |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
*M8 |
City Hall |
* Remark 1: Location ID has been updated from M7 to
M8 for City Hall
* Remark 2: M7e has become a reference station
starting from 7 Aug 2012
Real time Noise Monitoring
Stations
4.1.2.
The noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established Action/Limit Levels
for the monitoring works.
Table 4.2 Real Time Noise
Monitoring Stations
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD
Hong Kong Transport Section
Whitfield Depot |
North
Point |
RTN2a |
Hong Kong Electric
Centre |
North Point |
RTN3 |
Po Leung Kuk Yu Lee
Mo Fan Memorial School |
Tin Hau |
RTN4 |
Causeway Bay
Community Centre |
Noise
Monitoring Parameters, Frequency and Duration
4.1.3.
The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays.
For all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
4.1.4.
Noise monitoring shall be carried out at all
the designated monitoring stations. The monitoring frequency shall depend on
the scale of the construction activities. The following is an initial guide on
the regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
· One set of measurements between 0700
and 1900 hours on normal weekdays.
4.1.5.
Real time noise shall be carried out at the
designated monitoring stations. The following is an initial guide on the
regular monitoring frequency for each station on a 24 - hours basis when noise
generating activities are underway:
· One set of measurements between 0700
and 1900 hours on normal weekdays.
· One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
· One set of measurements between 2300
and 0700 hours on next day on everyday.
4.1.6.
If construction works are extended to include
works during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring
Equipment
4.1.7.
As referred to in the Technical Memorandum ™
issued under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.8.
Noise measurements shall not be made in fog,
rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10
m/s. The wind speed shall be checked with a portable wind speed meter capable
of measuring the wind speed in m/s.
4.1.9.
The sound level meter shall be checked using
an acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements will be accepted as valid only if the calibration level from before
and after the noise measurement agree to within 1.0 dB.
Air Quality
Monitoring Stations
4.2.1.
The air quality monitoring stations for the
Project are listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.3 Air Quality Monitoring
Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil
Street Site Office** |
North Point (Re-commenced on 14 November 2011) |
CMA2a |
Causeway
Bay Community Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza*** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: As
per the ENPC meeting in March 2011, the monitoring stations CMA3a – Future CWB
site office at Wanchai Waterfront Promenade was renamed as remark.
Remarks**: The
location ID of monitoring station CMA1b was updated as “Oil Street Site Office”
in April 2013.
Remarks***: The
station ID and monitoring location was updated in December 2014 with respect to
monitoring station relocation.
Air QUALITY Monitoring
Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The
24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
4.2.3.
All relevant data including temperature,
pressure, weather conditions, elapsed-time meter reading for the start and stop
of the sampler, identification and weight of the filter paper, and any other
local atmospheric factors affecting or affected by site conditions, etc., shall
be recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six days should be
undertaken when the highest dust impact occurs.
Sampling
Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance
with the following specifications shall be used for carrying out the 1-hour and
24-hour TSP monitoring:
· 0.6 – 1.7 m3 per minute
adjustable flow range;
· Equipped with a timing / control device
with +/- 5 minutes accuracy for 24 hours operation;
· Installed with elapsed-time meter with
+/- 2 minutes accuracy for 24 hours operation;
· Capable of providing a minimum exposed
area of 406 cm2;
· Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
· Equipped with a shelter to protect the
filter and sampler;
· Incorporated with an electronic mass
flow rate controller or other equivalent devices;
· Equipped with a flow recorder for
continuous monitoring;
· Provided with a peaked roof inlet;
· Incorporated with a manometer;
· Able to hold and seal the filter paper
to the sampler housing at horizontal position;
· Easily changeable filter; and
· Capable of operating continuously for a
24-hour period.
4.2.6.
Initial calibration of dust monitoring
equipment shall be conducted upon installation and thereafter at bi-monthly
intervals. The transfer standard shall be traceable to the internationally
recognized primary standard and be calibrated annually. The concern parties
such as IEC shall properly document the calibration data for future reference. All
the data should be converted into standard temperature and pressure condition.
Laboratory
Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature
and humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8” x 10” shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24 hours and
be pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with
dust shall be kept in a clean and tightly sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
4.2.10.
All the collected samples shall be kept in a
good condition for 6 months before disposal.
4.2.11.
Current calibration certificates of
equipments are presented in Appendix
4.2.
5.0.1.
The environmental monitoring will be
implemented based on the division of works areas of each designated project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure 2.1
and Figure 4.1. The monitoring results are
presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent
contracts are as follows:
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section)
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange
Contract no.
HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
Contract no.
HY/2010/08 – Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
Contract no. HK/2009/01
– Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre
Contract no.
HK/2009/02 - Wan Chai Development Phase II – Central - Wan Chai Bypass at Wan
Chai East
Contract no.
HK/2012/08 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai West
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB)– Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.0.3.
The environment monitoring schedules for
reporting month and coming month are presented in Appendix 5.1.
5.1.1
Monitoring for report of review baseline
noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20
June 2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for
the noise calculation starting from January 2012.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.1.2 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 5.1 below:
Table 5.1 Noise
Monitoring Stations for
Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
*
Remark: M7e has become a reference station starting from 7 Aug 2012
5.1.3
No action or limit level exceedance was
recorded in this reporting month.
5.1.4
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009 and Contract no.
HK/2009/02 – Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
5.1.5
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
noise monitoring stations are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract
no HK/2009/01
and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.6
No action or limit level exceedance was
recorded in this reporting month.
5.1.7
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.1.8 The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed divisions of
noise monitoring stations are summarized in Table 5.3 below.
Table 5.3
Noise Monitoring Stations
for Contract
no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.9
No action or limit level exceedance was
recorded in this reporting month.
5.1.10
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.1.11 Noise monitoring for the
tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The
proposed division of noise monitoring stations are summarized in Table 5.4
below.
Table 5.4 Noise
Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.1.12
Three limit level exceedances were recorded at
M6 – Hk Baptist Church Henrietta Secondary School on 03, 10 and 26 April 2017
in the reporting month.
5.1.13
Traffic noise was observed during monitoring
on 03, 10 and 26 April 2017 and were considered as the major noise
contribution. As such, the limit level exceedances were concluded as
non-project related.
5.1.14
One limit level exceedance was recorded at
M5b – City Garden on 18 April 2017 in the reporting month.
5.1.15
Starter bar fixing works and breaking works
at marine pier under Contract HY/2009/19 was conducted during the measurement
on 18 April 2017, it was observed that breaking operation was the major noise
contribution during measurement. It is concluded that the exceedance was
Project related and the contractor was requested to submit a proposal for
remediation measures following the Event and Action Plan. Actions from the
remediation plan including i) Closing the opening of the temporary noise
barrier ii) provide physical wrapping of breaker to dampen noise emission and
iii) conduct breaking works intermittently were implemented by the Contractor
and no further exceedance was recorded upon implementation of the remedial
actions.
5.1.16
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2. Details
of the Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-12/364/2009/D
5.1.17 The
commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02
September 2013. The proposed divisions of noise monitoring stations are
summarized in Table 5.5 below.
Table 5.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
5.1.18
No action or limit level exceedance was
recorded in this reporting month.
5.1.19
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.1.20 Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2011/08 are summarized in Table 5.6 below:
Table 5.6
Noise Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
* Remark: M7e has become a reference station
starting from 7 Aug 2012
5.1.21
No action or limit level exceedance was
recorded in this reporting month.
5.1.22
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
5.2.1.
Real time noise monitoring at RTN4-Causeway Bay Community Centre was
commenced on 13 Jan 2013. The baseline noise level of RTN4- Causeway Bay
Community Centre has adopted the results from the baseline noise monitoring
report for EP/364/2009 in 22 April 2010 in which approved by EPD.
5.2.2.
Po Leung Kuk Yu Lee Mo Fan Memorial School granted permission for set up
on 4 Sep 2012 and real time noise monitoring station RTN3 set up was performed
on 14 Sep 2012. Real time noise baseline capturing was conducted during time
period without construction work from 21 Sep 2012 to 04 Oct 2012. Real time noise monitoring at RTN3 – Po Leung Kuk Yu Lee Mo Fan Memorial School was
commenced since 06 Oct 2012.
5.2.3.
Real-time noise monitoring station RTN2 previously located at oil Street
Community Liaison Centre was relocated to Hong Kong Electric Centre on 5 Oct
2012, which is a representative of the noise sensitive receiver City Garden.
The baseline noise level of RTN2a will adopt the results derived from the
baseline noise monitoring conducted at Hong Kong Electric Centre from 4
December 2009 to 17 December 2009.
5.2.4.
Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely
adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with
respect to the commencement of advance works for IEC parapet demolition.
5.2.5.
With respect to the non-CWB Project building construction at Oil Street,
the real-time noise monitoring station RTN2a- Hong Kong Electric Centre was
finely adjusted from Northeast Side to Northwestern side at Roof Top location
on 03 March 2017.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.2.6.
The proposed division of noise monitoring
stations are summarized in Table 5.7 below. Real time noise
monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table 5.7 Real
Time Noise
Monitoring Stations for Contract
no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Hong Kong Electric Centre |
RTN3 |
North
Point |
Po Leung Kuk Yu Lee Mo Fan Memorial School |
RTN4 |
Tin
Hau |
Causeway Bay Community Centre |
* Real time noise monitoring results and graphical presentation during restrict
hours and night time period are for information only and noise during CNP
period shall be controlled under NCO.
5.2.7.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded in the reporting month.
5.2.8.
No limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded in the reporting month.
5.2.9.
No limit level exceedances were recorded at
RTN3- Yu Lee Mo Fan Memorial School in the reporting month.
5.2.10.
Limit level exceedance
was recorded at RTN4- Causeway Bay Community Centre were recorded on 20 and 21
April 2017 in the reporting month. After checking with Contractor HY/2009/19, no
construction works activity was conducted on 20 and 21 April 2017 during the
monitoring period while non - CWB breaking was observed conducted on the
monitoring dates immediately next to the monitoring station. As such, the
exceedances were concluded as non-Project related.
5.2.11.
Real time noise monitoring results measured
in this reporting period are reviewed and summarized. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 5.4.
Contract no. HY/2011/08 – Central - Wan Chai
Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning
5.2.12.
The proposed division of noise monitoring
stations are summarized in Table 5.8 below. Real time noise
monitoring for major construction works under contract no. HY/2011/08 was
commenced on 19 March 2015.
Table 5.8 Real
Time Noise
Monitoring Stations for Contract
no. HY/2011/08
Location
ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section
Whitfield Depot |
RTN2a |
North
Point |
Hong Kong Electric Centre |
RTN4 |
Tin Hau |
Causeway
Bay Community Centre |
* Real time noise monitoring results and
graphical presentation during restrict hours and night time period are for
information only and noise during CNP period shall be controlled under NCO.
5.2.13.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded in the reporting month.
5.2.15.
Limit level exceedance
was recorded at RTN4- Causeway Bay Community Centre were recorded on 20 and 21
April 2017 in the reporting month. After checking with Contractor HY/2011/08,
no construction works activity was conducted on 20 and 21 April 2017 during the
monitoring period while non - CWB breaking was observed conducted on the
monitoring dates immediately next to the monitoring station. As such, the
exceedances were concluded as non-Project related.
Contract no. HY/2009/18 –
Central – Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
5.3.1
Air quality monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.9 below.
Table 5.9 Air Quality Monitoring Stations for Contract
no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
5.3.2
No exceedance was recorded in the reporting
month.
5.3.3
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
5.3.4
The commencement of construction works for
Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality
monitoring stations are summarized in Table 5.10 below.
Table 5.10 Air Quality Monitoring Station for Contract
no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.5
No exceedance was recorded in the reporting
month.
5.3.6
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.3.7
The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of
air quality monitoring stations are summarized in Table 5.11
below.
Table 5.11 Air Quality Monitoring Station for Contract
no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
5.3.8
No exceedance was recorded in the reporting
month.
5.3.9
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/15 –
Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
5.3.10
The commencement of construction works for
Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Air
quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized
in Table 5.12 below.
Table 5.12
Air
Quality Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.11
No exceedance was recorded in the reporting
month.
5.3.12
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
5.3.13
The proposed division of air quality monitoring
stations are summarized in Table 5.13 below. Air quality monitoring
for the tunnel works under contract no. HY/2009/19 was commenced on 26 April
2011.
Table 5.13 Air Quality
Monitoring
Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
5.3.14
No exceedance was recorded in the reporting
month.
5.3.15
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2012/08- Wan Chai Development Phase
II – Central-Wan Chai Bypass at Wan Chai West
5.3.16
The commencement of construction works for
Contract no. HK/2012/08 under FEP-09/364/2009/B was on May 2014. Air quality
monitoring was commenced on 25 August 2011. The proposed division of air quality monitoring stations are summarized
in Table 5.14 below.
Table 5.14
Air
Quality Monitoring Station for Contract no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
5.3.17
No exceedance was recorded in the reporting
month.
5.3.18
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-12/364/2009/D
5.3.19
The commencement of construction works for
Contract no. HY/2010/08 under FEP-12/364/2009/D was on July 2014. Air quality
monitoring was commenced on 14 July 2011. The
proposed division of air quality monitoring stations are summarized in Table
5.15 below.
Table 5.15
Air
Quality Monitoring Station for Contract no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.20
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
5.3.21
Air quality monitoring for the Central
Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
5.16 below.
Table 5.16 Air
Quality Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
CMA1b |
Oil Street Site Office |
CMA2a |
Causeway Bay Community Centre |
CMA5b |
Pedestrian Plaza |
5.3.22
No exceedance was recorded in the reporting month.
5.3.23
Air quality monitoring results measured in
this reporting period are reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/01 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre – Tunnel Works under FEP-02/364/2009
5.4.1.
Inert C&D wastes and non-inert C&D wastes were disposed in this
reporting month. Details of the waste flow table are summarized in
Table 5.17.
Table 5.17 Details of Waste Disposal for Contract
no. HK/2009/01
Waste Type |
|||
Inert C&D materials disposed, m3 |
8.23 |
107951.65 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
Nil |
98512.03 |
N/A |
Non-inert C&D materials disposed, m3 |
5.16 |
5260.62 |
SENT Landfill |
Non-inert C&D materials recycled, kg |
Nil |
1285746 |
N/A |
Chemical waste disposed, kg |
Nil |
10400 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal) , m3 |
Nil |
11527 |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) &
Type 2 – Confined Marine Disposal) , m3 |
Nil |
16261 |
East of Cha Chau South Brothers |
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
5.4.2.
Inert C&D & non-inert C&D wastes
were disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.18.
Table 5.18 Details
of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
145 |
522040.412 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
Nil |
46520 |
N/A |
Non-inert C&D materials disposed, m3 |
132 |
4329.317 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
Nil |
N/A |
N/A |
Chemical waste disposed, kg |
Nil |
17718 |
N/A |
Marine Sediment (Type 1 – Open Sea Disposal)
, m3 |
Nil |
65663 |
South Cheung Chau |
Contract no.
HY/2009/18 – Central – Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
5.4.3.
Inert C&D and non-inert C&D waste was
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.19.
Table 5.19 Details
of Waste Disposal for Contract no. HY/2009/18
138.39 |
1415193.43 |
||
Nil |
58787.05 |
||
5.51 |
4363.05 |
||
Nil |
878.37 |
||
Nil |
6772 |
Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
5.4.4.
Inert & Non-inert C&D wastes were disposed of in this reporting
month. Details of the waste flow table are summarized in Table 5.20.
Table 5.20 Details of Waste Disposal for
Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials
disposed, m3 |
Nil Nil |
625200.92 245453.3 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled, m3 |
Nil |
358660.77 |
HY/2009/11 ex-PCWA TS4 /TS2 WDII Lun Ku Tan WENT HY/2010/08 |
Non-inert C&D
materials disposed, m3 |
Nil Nil |
4673.91 1.58 |
SENT Landfill WENT Landfill |
Non-inert C&D
materials recycled, m3 |
Nil |
5496446.2 |
Xun Xiang Metalware
Skylight Recycle (paper) |
Chemical waste disposed, kg |
Nil |
22755 |
Dunwell Group |
Marine Sediment
(Type1-Open Sea Disposal (Dedicate Sites) &Type 2 – Confined Marine
Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
5.4.5.
Inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.21.
Table 5.21
Details of Waste Disposal for
Contract no. HY/2009/19
Inert
C&D materials disposed, ton |
1119.58 |
676968.36 |
TM38 |
Inert
C&D materials recycled, ton |
Nil |
82349.7 |
N/A |
Non-inert
C&D materials disposed, ton |
60.37 |
5683.41 |
SENT Landfill |
Non-inert
C&D materials recycled, ton |
Nil |
565.63 |
N/A |
Chemical
waste disposed, kg |
Nil |
10.15 |
N/A |
Marine
Sediment (Tunnel) (Type-1 Open Sea Disposal), m3 |
Nil |
20556 |
South of Cheung Chau |
Marine
Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 –
Confined Marine Disposal), m3 |
Nil |
30751 |
East of Sha Chau |
Contract no. HK/2012/08 Wan Chai
Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
5.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.22.
Table
5.22 Details of Waste Disposal for Contract
no. HK/2012/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
448 Nil |
18714 116668 |
TKO 137 TM38 |
Inert
C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert
C&D materials disposed, m3 |
685 |
7367 |
SENT |
Non-inert
C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical
waste disposed, kg |
Nil |
Nil |
N/A |
Marine
sediment (Type 1) disposal, m3 |
Nil |
3145 |
South of Cheung Chau / East of Sha Chau / South
of The Brothers |
Remarks: The quantity of inert C&D material disposed, recycled,
non-inert C&D material disposed, recycled are reported up to calendar month
of April 2017.
Contract no. HY/2010/08
Central
– Wan Chai Bypass (CWB) – Tunnel (Slip Road 8) under FEP-10/364/2009/B
5.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.23.
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
520.7 Nil Nil 82.2 |
578665.57 262656.6 82911.8 72629.59 |
TM 38 WENT SENT TKO area 137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
309.3 |
4297.83 |
SENT |
Non-inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Chemical waste disposed, kg |
Nil |
979 |
N/A |
Type 1 – Open Sea Disposal, m3 |
Nil |
16368.4 |
East Sha Chau/ South Brothers Island |
Type 2 – Confined Marine disposal, m3 |
Nil |
549.2 |
East Sha Chau |
Table 5.23 Details of Waste Disposal for Contract no.
HY/2010/08
Contract no. HY/2011/08
Central
–Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
5.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.24.
Table
5.24 Details of Waste Disposal for
Contract no. HY/2011/08
Waste Type* |
Quantity this month |
Cumulative-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
16.78 |
678.89 |
CWPF & TKO137 |
Inert C&D materials recycled, m3 |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed, m3 |
205.82 |
2366.05 |
SENT |
Non-inert C&D materials recycled, ton |
Nil |
31.72 |
N/A |
Chemical waste disposed, kg |
Nil |
3800 |
N/A |
6.0.1.
The Event Action Plan for construction noise,
air qualities are presented in Appendix 6.1.
Contract no. HY/2009/18 – Central – Wan
Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
6.1.1.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Hong Kong Convention Exhibition Centre
– Tunnel Works under FEP-02/364/2009
6.1.2.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/02 – Wan Chai Development Phase II – Central – Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
6.1.3.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
6.1.4.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 – Central – Wanchai
Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.5.
Three limit level exceedances were recorded
at M6 – Hk Baptist Church Henrietta Secondary School on 03, 10 and 26 April
2017 in the reporting month.
6.1.6.
Traffic noise was observed during monitoring
on 03, 10 and 26 April 2017 and were considered as the major noise
contribution. As such, the limit level exceedance was concluded as non-project
related.
6.1.7.
One limit level exceedance was recorded at M5b
– City Garden on 18 April 2017 in the reporting month.
6.1.8.
Starter bar fixing works and breaking works
at marine pier under Contract HY/2009/19 was conducted during the measurement
on 18 April 2017, it was observed that breaking operation was the major noise
contribution during measurement. It is concluded that the exceedance was
Project related and the contractor was requested to submit a proposal for
remediation measures following the Event and Action Plan. Actions from the
remediation plan including i) Closing the opening of the temporary noise
barrier ii) provide physical wrapping of breaker to dampen noise emission and
iii) conduct breaking works intermittently were implemented by the Contractor
and no further exceedance was recorded upon implementation of the remedial
actions.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.1.9.
No exceedance was recorded in the reporting
month.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/E
6.1.10.
No exceedance was recorded in the reporting
month.
Real Time Noise Monitoring
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.1.11.
No limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot was recorded in the
reporting month.
6.1.12.
No limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded in the reporting month.
6.1.13.
No limit level exceedances were recorded at
RTN3- Yu Lee Mo Fan Memorial School in the reporting month.
6.1.14.
Limit level exceedance was recorded at RTN4-
Causeway Bay Community Centre were recorded on 20 and 21 April 2017 in the
reporting month. After checking with Contractor HY/2009/19, no construction
works activity was conducted on 20 and 21 April 2017 during the monitoring
period while non - CWB breaking was observed conducted on the monitoring dates
immediately next to the monitoring station. As such, the exceedances were
concluded as non-Project related.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009/EF
6.1.15.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded in the reporting month.
6.1.16.
No limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded in the reporting month.
6.1.17.
Limit level exceedance
was recorded at RTN4- Causeway Bay Community Centre were recorded on 20 and 21
April 2017 in the reporting month. After checking with Contractor HY/2011/08,
no construction works activity was conducted on 20 and 21 April 2017 during the
monitoring period while non - CWB breaking was observed conducted on the
monitoring dates immediately next to the monitoring station. As such, the
exceedances were concluded as non-Project related.
Contract no. HY/2009/18 – Central – Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
6.2.1.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/01 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition
Centre – Tunnel Works under FEP-02/364/2009
6.2.2.
No exceedance was recorded in the reporting
month.
Contract no. HK/2009/02 – Wan Chai
Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
6.2.3.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/15 – Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
6.2.4.
No exceedance was recorded in the reporting
month.
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
6.2.5.
No exceedance was recorded in the reporting
month.
Contract no. HK/2012/08 Wan Chai Development Phase
II - Central-Wan Chai Bypass at Wan Chai West under FEP-12/364/2009/D
6.2.6.
No exceedance was recorded in the reporting
month.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
6.2.7.
No exceedance was recorded in the reporting
month.
Contract no. HY/2011/08
Central
–Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and
Works Associated with Tunnel Commissioning under FEP-11/364/2009/E
6.2.1
No exceedance was recorded in the reporting
month.
6.3.1.
There was no non-compliance from the site
audits in the reporting period. The observations and recommendations made in
each individual site audit session were presented in Section 8.
6.3.2.
One project related limit level exceedance
was recorded at M5b – City Garden on 18 April 2017 in the reporting month. The
exceedance was concluded as related to the breaking works at marine pier under
Contract HY/2009/19.
6.4.1
No particular action taken was taken for site
audits since no non-compliance was recorded in the reporting period.
6.4.2
Starter bar fixing works and breaking works
at marine pier under Contract HY/2009/19 was conducted during the measurement
on 18 April 2017, it was observed that breaking operation was the major noise
contribution during measurement. It is concluded that the exceedance was
Project related.
6.4.3
The contractor was requested to submit a
proposal for remediation measures following the Event and Action Plan. Actions
from the remediation plan including i) Closing the opening of the temporary
noise barrier ii) provide physical wrapping of breaker to dampen noise emission
and iii) conduct breaking works intermittently were implemented by the
Contractor and no further exceedance was recorded upon implementation of the
remedial actions.
7.0.1.
According to Condition 3.4 of the
EP-364/2009/E, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Final
EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02,
the major construction activities were completed by end of January 2014 and no
construction activities were undertaken thereafter and the water
quality monitoring was completed in October 2011. As such, it is considered that there
were no cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting month.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area include road works, backfilling works and reinstatement of Culvert and
Cooling mains were performed in April 2017 reporting month. As no project
related exceedance were recorded during the reporting period, cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was considered as insignificant.
7.0.4.
According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activities under Wan Chai Development Phase II were, road and drains
construction, backfilling works, and tunnel works at Wan Chai West, tunnel
construction, backfilling works, road and drains works at Wan Chai West and Wan
Chai East. The major construction activities under Central-Wan Chai Bypass and
Island Eastern Corridor Link Projects were drainage works and ventilation building
construction at Central; backfilling and temporary reclamation removal works at
Causeway Bay road works and side wall construction at Victoria Park; reinstatement
of Eastern Breakwater and bridge demolition, noise enclosure installation, piling
works and tunnel works at North Point area in the reporting month. In addition,
other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island
Eastern Corridor Link projects was
observed undertaken at Wan Chai North and North Point area.
7.0.5.
No significant air quality impact from
construction activities was anticipated in the reporting month. Besides, no project
related exceedance was recorded during the air quality and noise environmental
monitoring events in the reporting month. Thus, it is evaluated that the
cumulative construction impact from the concurrent projects including Central
Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was
insignificant.
8.0.1.
During this reporting month, weekly
environmental site audits were conducted for Contracts no. HY/2009/15,
HY/2009/18, HY/2009/19, HK/2012/08, HK/2009/01, HK/2009/02, HY/2010/08 and HY/2011/08.
No non-conformance was identified during the site audits. The Contractors rectified major
observations and recommendations made during the audit sessions. No
non-conformance was identified during the site inspections.
8.0.2.
Site inspections for Contract no. HY/2009/15
were carried out during this reporting period. No observation
was found in the reporting month.
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
170330_01 |
30 Mar
2017 |
Vehicle
control for wheel washing at Gate 6 shall be strengthen to avoid muddy trail
on public road and washed muddy effluent flow into nearby public drain. |
No muddy
trail and washing effluent discharge observed at Gate 6. |
Completion
as observed on 4 April 2017 |
170406_01 |
4 Apr 2017 |
Drip tray
shall be provided for oil containers at Portion 5. |
Drip tray
was provided for oil container at Portion 5. |
Completion
as observed on 11 April 2017 |
170411_01 |
11 Apr
2017 |
Drip Tray
shall be provided for oil container at Portion 5. |
Drip tray
was provided for oil container at Portion 5. |
Completion
as observed on 18 April 2017 |
170418_01 |
18 Apr
2017 |
Silt
screen for RW21-P789 intakes shall be properly maintained and ensure the
curtain is fully extended to seabed level. |
Silt
screen was deployed orderly and maintained. |
Completion
as observed on 27 April 2017 |
8.0.7.
Site inspection for Contract no. HK/2012/08
were carried out during this reporting period. The results of these inspections
and outcomes are summarized in Table 8.6.
Table 8.6 Summary
of Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action taken
by Contractor |
Completion date |
170405_01 |
5-Apr-17 |
Contractor
is required to critically review the capacity and operation of the water
treatment unit at Slip Road 1 to ensure the construction effluent is properly
treated prior discharge and safeguard nearby waterbody. |
The
concerned water treatment unit at Slip Road 1 was observed disconnected and
no discharge was observed. |
Completion
as observed on 11 April 2017 |
170405_02 |
5-Apr-17 |
Drip tray
shall be provided for chemical containers at Zone CE. |
Chemical
containers was removed at Zone CE. |
Completion
as observed on 11 April 2017 |
170411_01 |
11-Apr-17 |
Drip tray
shall be provided for oil containers on-site. |
Drip tray
was provided for oil containers on-site |
Completion
as observed on 19 April 2017 |
170425_01 |
25-Apr-17 |
Drip tray
shall be provided for the chemical container at dry dock area. |
Chemical
container at dry dock area was removed. |
Completion
as observed on 2 May 2017 |
170425_02 |
25-Apr-17 |
The
hole of drip tray for the generator at dry dock area shall be covered. |
The
hole of drip tray was covered. |
Completion
as observed on 2 May 2017 |
Table 8.7 Summary
of Environmental Inspections for Contract no. HY/2010/08
Item |
Date |
Observations |
Action
taken by Contractor |
Completion date |
170329_1 |
29 Mar
2017 |
Localized
impermeable barrier shall be provided to underwater excavation works area and
construction sequence shall be critically review to avoid muddy dispersion
when derrick barge depart from site (TS3 North
West) |
Impermeable
barrier was provided to underwater excavation works to avoid muddy dispersion |
Completion
as observed on 7 Apr 2017 |
170329_2 |
29 Mar
2017 |
Mud / Silt
sitting on the edge of seawall shall be cleaned more frequently to avoid drop
off (TS3
North, TS3 East) |
Mud / Silt
sitting on the edge of seawall was cleaned |
Completion
as observed on 7 Apr 2017 |
170329_3 |
29 Mar
2017 |
NRMM Label
shall be provided to excavator (TS3 East) |
The
concerned excavator was departed from site |
Completion
as observed on 7 Apr 2017 |
170407_1 |
7 Apr 2017 |
Seawall
block lifting hole cleaning operation shall be enclosed by silt
curtain/impermeable barrier to avoid muddy dispersion (TS3 North
West) |
Silt
curtain was deployed to enclose the working area at concerned location |
Completion
as observed on 12 Apr 2017 |
170407_2 |
7 Apr 2017 |
Derrick
barge for conducting under-water excavation shall be enclosed by silt curtain
to avoid potential dispersion (TS3 West) |
No further
underwater excavation was observed at the concerned location |
Completion
as observed on 12 Apr 2017 |
170412_1 |
12 Apr
2017 |
Impermeable
barrier shall be deployed to the seabed and enclosed the underwater excavation
area (-4.35mPD to -7mPD) to avoid muddy dispersion (TS3
North) |
Impermeable
barrier was deployed to the
seabed and enclosed the underwater excavation area |
Completion
as observed on 2 May 2017 |
170426_1 |
26 Apr
2017 |
Silt
curtain shall be deployed to enclose the working area of seawall lifting and
material transfer (TS3 North
and West) |
No further
seawall lifting works was observed |
Completion
as observed on 2 May 2017 |
8.0.9.
Site inspections for Contract no. HY/2011/08
were carried out during this reporting period. No observation was found in the
reporting month.
9.0.1.
No environmental complaints were received in the reporting month.
9.0.2.
Two Summons to Defendant (Case No. ESS38444/2016 and Case No.ESS38443/2016)
were issued to the Contractor(s) under Contract HY/2009/19 on 06 October 2016
regarding the case against (Regulations 4(1) and 4(2) of the Air Pollution
Control (Construction Dust) Regulation made under section 43 of the Air
Pollution Control Ordinance, Cap311 were notified to the Environmental Team on
31 March 2017.
9.0.3.
The offence under the two Summons to Defendant (Case No. ESS38444/2016
and Case No.ESS38443/2016) were issued to the Contractor(s) under Contract
HY/2009/19 on 06 October 2016 regarding the case against (Regulations 4(1) and
4(2) of the Air Pollution Control (Construction Dust) Regulation made under
section 43 of the Air Pollution Control Ordinance, Cap311 were convicted on 03
April 2017.
9.0.4.
Two Summons to Defendant (Case No. ESS40680/2016 and Case No.
ESS40679/2016) were issued to the Contractor(s) under Contract HY/2009/19 on 25
October 2016 regarding the case against Section 6(1)(b) and 6(5), Noise Control
Ordinance Cap 400 on 31 March 2017 and pending for case hearing.
9.0.5.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.6. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table 9.1 Cumulative Statistics on
Complaints
Reporting Period |
No. of Complaints |
April 2017 |
0 |
September 2010 – March 2017 |
78 |
Total |
78 |
Table
9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
1 (05 April 2016) |
1 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
1 |
1 |
10.0.1.
The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
10.0.2.
The scheduled construction activities and the
recommended mitigation measures for the coming month are listed in Table
10.1. The construction programmes of individual contracts are provided
in Appendix 10.1.
Table 10.1 Summary
of Key Construction Activities of Individual Contract(s) to be commenced in
Coming Reporting Month
Contract No. |
Key Construction
Works |
Recommended Mitigation Measures |
HY/2009/15 |
·
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE
and TPCWAW ·
Reinstatement work at the PRE Office car park area ·
Re-surfacing work at Hung Hing Road |
·
Dust control during dust generating activities and covering for
stockpile stored on site. ·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the nearby water. ·
Maintain regular cleaning of floating refuses within construction
area. |
HY/2009/18 |
·
Drainage works ·
Road works ·
Landscaping works ·
Maintenance works |
·
Dust control during dust generating activities ·
Provide protection works to ensure no runoff out of site area or
direct discharge into public drainage system. |
HY/2009/19 |
·
Approach ramp sheet piling, pre-bored piling and top soil removal works ·
Hing Fat Street modification works ·
Bridge Demolition / Construction ·
Hotel Carpark Reinstatement ·
Oil Street drainage works ·
Bridge E noise barrier installation ·
IEC noise enclosure/barrier installation ·
Excavation / Construction of retaining wall ·
Removal of temporary works including beams, columns and footings for
TB bridge ·
Installation of skin parapet on TB bridge ·
Construction of metal roof for FEHD |
·
Noise level shall be controlled by reducing the breaking operation
rate. ·
Noise barrier shall be implemented ·
Dust control during dust generating works ·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. |
HK/2009/01 |
·
Reinstatement of amenity area ·
Road and Drain works |
·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system or the sea. ·
Dust control during dust generating works ·
Noise mitigation measures during breaking works |
HK/2009/02 |
·
Rectification works for the defects for the end of maintenance period
of Observation Deck and Staircase ST-01. ·
Rectification works for cross road ducts ·
Rectification works for
cracks/joints with water leakage inside OHVD cells ·
Tunnel backfilling (rock fill Type A, Type B and filter material) ·
Construction of temporary wall. ·
Concreting blinding layer for Hung Hing Road flyover. ·
Rebar fixing and concreting of HHR flyover. ·
Remedial works of tunnel wall, base slab and OHVD. ·
General cleaning and rectification works of OHVD, tunnel base slab,
carrier drain, cross road duct and manhole gully. ·
Rebar fixing and concreting of base slab and walls. ·
Rebar fixing and concreting of roadside barrier. ·
Rebar fixing and concreting of OHVD slab. ·
Rebar fixing and concreting of top slab. ·
Erect scaffolding for OHVD and top slab. ·
Tree Pruning Works at Fleming Road (VO No. 237) ·
Tree pruning works at Fleming Road ·
Sewage Works at Hung Hing Road and Wan Shing Street ·
Trial pit at Hung Hing Road for sewage works. ·
Construction of manhole for Wan Shing Street sewage works |
·
Dust control during dust generating works ·
Proper maintenance boundary surface runoff protection and water
treatment facilities to avoid potential runoff related impact. ·
Provision of protection measures to ensure no runoff out of site area
or direct discharge into public drainage system. |
HK/2012/08 |
·
Grouting ·
Construction of Slip Road 1 ·
Construction of drainage ·
Back-filling at CWB tunnel |
·
Dust control during dust generating works ·
Provide protection works and adequate drainage system to ensure no
direct discharge into public drainage system. |
HY/2010/08 |
·
Tree protection works next to existing BGO, ·
Drainage improvement works, ·
Utility diversion works, ·
Retaining wall works ·
ELS works, ·
Construction works for subway extension |
·
Dust control during dust generating works and stockpile stored on
site. ·
Appropriate measures should be taken to ensure adequate protections
are provided for trees being transplanted and retained on site. ·
Provision of protection to ensure no runoff out of site area or
direct discharge into public drainage system. |
HY/2011/08 |
·
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building,
West Ventilation Building ·
Construction of Tunnel Thermal Barrier ·
Installation of Electricals and Mechanicals ·
Installation of Tunnel Features |
·
Dust control during dust generating works |
10.0.3.
The construction works of Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
10.0.4.
The construction works of Contract no.
HY/2009/17 - Advance piling works at Whitfield Depot under FEP-03/264/2009 was
completed, and the FEP was surrendered by the Contractor and found in order by
EPD on 25 April 2013.
10.0.5.
The construction works of Contract HK/2010/06
was completed, and the FEP-08/364/2009/A was surrendered by the Contractor on 3
October 2014.